Ringwood East Station and elevated rail structure at night

SEPA — Dublin Road

Two level crossings removed and a new Ringwood East Station delivered — making Ringwood level crossing free.

Location
Melbourne, VIC
Completion
2024
Client
Laing O'Rourke
Project Value
$20M

Ringwood is now level crossing free

The level crossings at Dublin Road, Ringwood East and Bedford Road, Ringwood, have been removed making Ringwood level crossing free.

The new Ringwood East Station opened in July and features a main concourse and second entry, platforms that are accessible by lifts and stairs, and upgraded pedestrian and cycling paths.

The new station will create safer and more direct links between the Ringwood East shopping precinct, public transport and upgraded parking with about 460 car spaces.

Around 23,000 vehicles travelled through these former level crossings each day, where the boom gates were down for up to 23 minutes during peak morning periods.

Project location

Scope of works

Rail, station and precinct works delivered around live train operations and a busy retail centre.

  • 01Level crossing removals

    Dublin Road, Ringwood East and Bedford Road, Ringwood level crossings removed.

  • 02New Ringwood East Station

    A main concourse and second entry, with platforms accessible by lifts and stairs.

  • 03Pedestrian & cycling paths

    Upgraded paths creating safer, more direct links to the Ringwood East shopping precinct and public transport.

  • 04Upgraded parking

    About 460 car spaces provided as part of the precinct upgrade.

Level Crossing RemovalStation WorksRail InfrastructurePrecinct Upgrade

Project questions

Which level crossings were removed?

The level crossings at Dublin Road, Ringwood East and Bedford Road, Ringwood — making Ringwood level crossing free.

What does the new Ringwood East Station include?

A main concourse and second entry, platforms accessible by lifts and stairs, upgraded pedestrian and cycling paths, and about 460 car spaces.

How busy were the former crossings?

Around 23,000 vehicles travelled through them each day, with boom gates down for up to 23 minutes during peak morning periods.

Need experienced people on a major project?